Court Case – Oracle Security Services Ltd v Barts Health NHS Trust


The court declined to grant summary judgment on a claim for an alleged breach of the Public Contracts Regulations 2015 Pt 2 (2) reg.33(7). Summary judgment had been sought on the basis that the claim had been brought outside the limitation period specified by reg.92(2), but the court found triable issues relating to when the claimant had acquired the requisite knowledge to start time running. In obiter remarks, the court observed that time began to run under reg.92(2) on the date that the requisite knowledge accrued, not the following day.