This PPN sets out how payment approaches can be taken into account in the procurement of major government contracts. It replaces PPN 08/21 from 1 April 2024.
Where this PPN applies, In-Scope organisations must use the questions in
Part 3 (Technical and Professional Ability) in the standard selection
questionnaire2. The questions require bidders to demonstrate they are paying 95% of invoices within 60 days (90% with an action plan), and also paying all their invoices within an average of 55 days.